The weather has been very cooperative for construction. The footings, foundation walls and slab were poured during the first week of the month, all appropriate inspections were done and approved. The framing of the pool building and rough subcontractor work followed directly behind the foundation curing time. The storm drain and driveway heat melt system were relocated and reinstalled during the month. The metal roof over the entry to the pool building was constructed and installed. Demolition of the glass foyer is underway. This portion of the project will create the inside entry to the pool.

Our website has pictures of the progress being made.

Based on current projections, Mint construction estimates the job will be completed around February 23, 2022.